PRINCE2 Foundation — Question 144
Which is an objective of the 'controlling a stage' process?
Answer options
- A. To review the business justification for the project
- B. To replan the current stage when directed
- C. To develop products to defined quality criteria
- D. To produce a team plan for the work package
Correct answer: D
Explanation
The correct answer, D, focuses on creating a team plan for the work package, which is essential for managing tasks effectively. Options A and C relate to broader project goals and quality, while B deals with replanning, which is not the primary objective of this process.