PRINCE2 Foundation — Question 140
How should the 'managing a stage boundary' process be used towards the end of a project's final delivery stage?
Answer options
- A. To plan the activities of the 'closing a project process
- B. To implement any exception plan requests from the project board
- C. To create a benefits management approach for corporate, programme management or the customer
- D. To review an issue received from a team manager
Correct answer: A
Explanation
The correct answer is A because the 'managing a stage boundary' process is intended to ensure that all necessary planning for project closure is completed before final delivery. Options B, C, and D do not directly relate to the planning of closing activities and focus on different aspects of project management.