PRINCE2 Foundation — Question 14

Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

Answer options

Correct answer: B

Explanation

The correct answer is B, Manage by exception, as it involves setting tolerances to allow for effective governance and decision-making when deviations occur. The other options do not specifically relate to the setting of tolerances; A focuses on project phases, C is about justifying ongoing business needs, and D emphasizes learning from past experiences.