PRINCE2 Foundation — Question 14
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
Answer options
- A. Manage by stages
- B. Manage by exception
- C. Continued business justification
- D. Learn from experience
Correct answer: B
Explanation
The correct answer is B, Manage by exception, as it involves setting tolerances to allow for effective governance and decision-making when deviations occur. The other options do not specifically relate to the setting of tolerances; A focuses on project phases, C is about justifying ongoing business needs, and D emphasizes learning from past experiences.