PRINCE2 Foundation — Question 130
Which is an objective of the Directing a Project process?
Answer options
- A. Create and authorize the project mandate
- B. Provide management control and direction
- C. Control the day-to-day running of the project
- D. Provide accurate progress information to the Project Manager
Correct answer: B
Explanation
The correct answer is B because the Directing a Project process is primarily focused on providing management control and direction to ensure the project aligns with its objectives. Options A, C, and D are important aspects of project management but do not specifically capture the essence of directing a project.