PRINCE2 Agile Practitioner — Question 4
Which is a benefit that can be realized by a PRINCE2 organization seeking to adopt PRINCE2 Agile?
Answer options
- A. Comprehensive documentation is reduced as working software is a priority.
- B. Reduced number of roles by combining project manager with team manager.
- C. Lower cost of ownership throughout the life of the project's delivered product(s).
- D. Improved maintenance of a business case throughout the project.
Correct answer: A
Explanation
The correct answer is A because PRINCE2 Agile emphasizes delivering functional software over extensive documentation, thereby reducing the amount of documentation needed. Options B, C, and D do not accurately reflect the primary benefits associated with adopting PRINCE2 Agile, as they focus on different aspects rather than the core philosophy of prioritizing working software.