PRINCE2 Agile Practitioner — Question 30
Which statement BEST describes the PRINCE2 Agile view of agile?
Answer options
- A. It is a related set of behaviours, concepts, frameworks and techniques.
- B. Exceptions are due to time being forecast to exceed agreed tolerances.
- C. It focuses on delivering comprehensively documented software.
- D. Tracking of features and progress is less important than tracking cost.
Correct answer: A
Explanation
The correct answer, A, accurately encapsulates the essence of PRINCE2 Agile by highlighting its comprehensive nature involving various behaviours and techniques. Options B, C, and D misrepresent the agile philosophy by focusing on exceptions, documentation, and cost tracking, which do not align with the agile emphasis on flexibility and iterative development.