PRINCE2 Agile Practitioner — Question 17
Which BEST describes one of the eight guidance points regarding PRINCE2 Agile?
Answer options
- A. Using agile and using Scrum is the same thing.
- B. Kanban specifies the need for a project manager role.
- C. Nothing needs to be removed to enable PRINCE2 to work with agile.
- D. PRINCE2 Agile recognizes that some projects are agile and others are not.
Correct answer: D
Explanation
The correct answer, D, emphasizes that PRINCE2 Agile accepts the reality that projects may vary in their agility. Options A and B present misconceptions about agile methodologies, as they incorrectly equate different frameworks and roles. Option C inaccurately suggests that PRINCE2 must be altered for agile compatibility, which is not the case.