PRINCE2 Agile Foundation — Question 6

In Scrum, what answers the question 'what can be done this sprint?'

Answer options

Correct answer: C

Explanation

The correct answer is C, Sprint planning, as it is the event where the team decides what can be achieved in the upcoming sprint. The Daily scrum is a check-in for progress, the Sprint review is for discussing completed work, and the Increment refers to the result of all completed work, not the planning process.