PRINCE2 Agile Foundation — Question 52
Which statement about the ‘directing a project’ process is CORRECT?
Answer options
- A. The project board may pull reports from the information radiator
- B. As a minimum, the project board should receive oral reports from the project manager
- C. The project board should attend the delivery team’s daily stand up meeting
- D. The project board should receive regular reports focusing on cost and time overruns
Correct answer: A
Explanation
Option A is correct because the project board indeed has access to reports from the information radiator, which provides valuable insights. Option B is incorrect as receiving oral reports is not the minimum requirement; written reports are typically preferred. Option C is wrong since the project board does not need to attend daily stand-up meetings, which are primarily for the delivery team. Option D is also incorrect because while updates on cost and time are important, the focus should be broader than just these overruns.