PRINCE2 Agile Foundation — Question 49
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
Answer options
- A. To use empiricism, based on knowledge that comes from experience
- B. To build, measure, learn from your experiences
- C. To create a minimum viable product to manage uncertainty
- D. To fail fast, if you are going to fail
Correct answer: A
Explanation
The correct answer is A because empiricism, while important, is not explicitly one of the core Lean Startup concepts. Options B, C, and D all represent key principles that focus on iterative development, learning from feedback, and managing risk through rapid prototyping.