How should product-based planning be used as part of PRINCE2 Agile?
Answer options
- A. To track progress against the team plan
- B. To create the project plan using empiricism
- C. To enable team planning to be predictive
- D. To plan by focusing on the features required
Correct answer: D
Explanation
The correct answer is D because product-based planning in PRINCE2 Agile emphasizes identifying and prioritizing the features that need to be delivered. Options A and C do not align with the core principle of focusing on product features, while option B incorrectly suggests that the project plan should be created solely through empirical methods.