PRINCE2 Agile Foundation — Question 42

What information is NOT typically displayed on a burn chart?

Answer options

Correct answer: B

Explanation

The correct answer is B, as burn charts primarily track progress by showing the effort remaining, actual work done, and elapsed time. The 'definition of ready' is a concept used in agile methodologies to describe when a user story is considered ready for development, but it is not represented visually on a burn chart.