PRINCE2 Agile Foundation — Question 38
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
Answer options
- A. Preferable
- B. Typical
- C. Effective
Correct answer: C
Explanation
The correct answer is 'Effective' because it highlights the successful integration of agile and traditional methodologies to enhance project management. 'Preferable' and 'Typical' do not accurately capture the effectiveness of this hybrid approach in tracking progress.