PRINCE2 Agile Foundation — Question 36
Which statement about velocity is CORRECT?
Answer options
- A. It is based on the concept of rationalism
- B. It is shown by the ideal line on a bum-down chart
- C. It describes how much work is getting done
- D. It tracks the time and cost of a timebox
Correct answer: C
Explanation
The correct answer is C, as velocity measures the amount of work completed in a given timeframe. Options A and B are incorrect because they do not relate to the definition of velocity in project management. Option D misrepresents velocity, as it does not track time and cost but rather focuses on work output.