PRINCE2 Agile Foundation — Question 3

What needs to happen when new detailed requirements are added to a timebox?

Answer options

Correct answer: A

Explanation

The correct answer is A because when new detailed requirements are added, it's essential to maintain the timebox's scope and ensure that the team's workload remains manageable by removing requirements of similar effort. Options B and C do not address the scope management required in a timebox, and option D, while related to change management, does not directly resolve the issue of managing existing requirements.