What needs to happen when new detailed requirements are added to a timebox?
Answer options
- A. Requirements of a similar level of effort should be removed
- B. More people should be added to the delivery team
- C. The delivery milestones should be reviewed and re-planned
- D. Formal change control should be applied
Correct answer: A
Explanation
The correct answer is A because when new detailed requirements are added, it's essential to maintain the timebox's scope and ensure that the team's workload remains manageable by removing requirements of similar effort. Options B and C do not address the scope management required in a timebox, and option D, while related to change management, does not directly resolve the issue of managing existing requirements.