PRINCE2 Agile Foundation — Question 22
When should PRINCE2 Agile be used?
Answer options
- A. When a team is created to deliver a specific product
- B. When delivering an ongoing service to a customer
- C. When an established team performs product maintenance
- D. When simple requests to update a product are implemented
Correct answer: A
Explanation
PRINCE2 Agile is best suited for projects where a team is formed specifically to deliver a unique product, allowing for flexibility and adaptability in project management. The other options relate to ongoing services or maintenance, which do not align with the primary goal of PRINCE2 Agile to manage product delivery with an agile approach.