PRINCE2 Agile Foundation — Question 11
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
Answer options
- A. It reduces testing in order to meet deadlines
- B. It sets the project baseline at the correct level
- C. It enables team dynamics to remain the same
- D. It improves the supplier's reputation with the customer
Correct answer: A
Explanation
The correct answer, A, highlights that to meet deadlines, there may be a tendency to reduce testing, which can compromise quality. Options B and C do not directly address the implications of being on time, while D focuses on reputation rather than the operational aspect of flexible delivery.