Project Management Professional (PMP) — Question 954

A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because it is essential to keep stakeholders informed and involved in significant changes to risk management strategies. Option B is incorrect as it suggests a step that may not be necessary if stakeholder review is prioritized. Option C overlooks the need for stakeholder engagement, and option D is not applicable since using management reserves is not the first step when a new response plan is available.