Project Management Professional (PMP) — Question 917

In a functional organization, a product analyst is assigned to a short-duration application development effort. The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D, as it promotes collaboration and provides the analyst with the necessary support to overcome their concerns while still allowing them to work on the task. Option A does not address the analyst's immediate concerns effectively. Option B removes the analyst from the task without addressing their need for support, and option C does not leverage the analyst's potential effectively, as it shifts the responsibility without proper guidance.