Project Management Professional (PMP) — Question 915

A new relevant project stakeholder suggested a change to some of the project parameters midway through execution. What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because evaluating the proposed change with integrated change controls allows for a thorough assessment of its impact on the project, and discussing it with the project sponsor ensures alignment with project objectives. Option A is incorrect as rejecting changes without evaluation can hinder project responsiveness. Option B is not ideal as it bypasses the necessary evaluation process, and option D is inappropriate since simply accepting changes without assessment can lead to uncontrolled project alterations.