Project Management Professional (PMP) — Question 913

A globally distributed project team is running behind schedule due to the lack of team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?

Answer options

Correct answer: A

Explanation

The correct answer is A, as conducting a root cause analysis will help identify the underlying issues causing low morale and commitment. Options B and D may not address the immediate problems effectively, while C, although useful, does not focus on understanding the root causes of the issues.