Project Management Professional (PMP) — Question 904

In an advanced stage of a project, a stakeholder who is not receiving the project status report communicates this to the project manager. After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because it directly addresses the oversight by updating the communications management plan and ensuring the stakeholder receives the necessary information. Option B is incorrect as it does not rectify the situation. Option C, while informative, does not solve the immediate issue, and D is not appropriate as it dismisses the stakeholder's right to information despite their registration.