Project Management Professional (PMP) — Question 888

There are two interdependent projects: the first project is in execution, and the second one is about to be deployed. The first project has been delayed, which is now affecting the second project due to the sharing of resources.

What should the project manager do in this situation?

Answer options

Correct answer: B

Explanation

The correct answer is B because it focuses on assessing resource availability and planning to deploy additional resources, which directly addresses the impact of the first project's delay. Option A is not effective as it simply seeks assurance without resolving the resource allocation issue. Option C communicates a delay but does not provide a solution to mitigate the resource shortage. Option D may introduce external resources, but it doesn't prioritize resolving the immediate resource allocation challenges.