A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need or access to water. What should the project manager do next?
Answer options
- A. Start project planning and develop the project management plan.
- B. Process a change request for additional funding due to project urgency.
- C. Hire local contractors who are familiar with the environment.
- D. Face the challenge immediately and start sending relief to the town.
Correct answer: A
Explanation
The correct answer is A because initiating project planning and developing a project management plan are crucial first steps to ensure the project's success and organization. Options B, C, and D may be important later but do not address the immediate need for a structured approach to manage the project effectively.