A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need or access to water. What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because initiating project planning and developing a project management plan are crucial first steps to ensure the project's success and organization. Options B, C, and D may be important later but do not address the immediate need for a structured approach to manage the project effectively.