Project Management Professional (PMP) — Question 865
A new project needs to be kicked off in an organization that has regulatory requirements defined in their organizational governance process. How should the project manager define the project governance?
Answer options
- A. Ask the project management office (PMO) if the regulatory requirements can be ignored.
- B. Update the project governance to include the current regulatory requirements.
- C. Customize all of the regulatory requirements to fit within the specific project governance.
- D. Update some of the regulatory requirements to fit within the project governance.
Correct answer: B
Explanation
The correct answer is B because it is essential for the project manager to integrate current regulatory requirements into the project governance to ensure compliance. Options A and C are inappropriate as ignoring regulations or completely customizing them would risk non-compliance. Option D may not adequately address the need for comprehensive governance by only modifying some requirements.