Project Management Professional (PMP) — Question 843

A bank has initiated a project to replace an existing core system with a new one. The system will be launched in several stages after the completion of each project deliverable that must be approved by the key stakeholders.

What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C, as agreeing on quality standards is fundamental to ensure that all project deliverables meet the expectations of stakeholders. Options A, B, and D, while important, are secondary steps that should follow the establishment of quality standards to guide the project's direction.