Project Management Professional (PMP) — Question 833

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because involving the project team can lead to collaborative solutions and ensure that all perspectives are considered in securing testing resources. Options A and B do not leverage the team’s collective input and may overlook internal capabilities. Option D proposes altering the project scope, which may not be the best course of action when internal resources can potentially be mobilized.