Project Management Professional (PMP) — Question 831

A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.

How should the project manager proceed?

Answer options

Correct answer: B

Explanation

The correct answer is B because calculating the costs and comparing the net present value (NPV) allows for a comprehensive financial evaluation of all options. The other choices, while useful analyses, do not provide the same level of financial insight or direct comparison needed to make an informed decision about the expansion.