Project Management Professional (PMP) — Question 815

Due to price inflation, an agile project manager has identified that the available project funding will not be enough to bring on an additional team member for the upcoming iterations as initially planned. The project budget and release deadlines are tight. The existing cross-functional team is experienced.

What is the first approach the project manager should take?

Answer options

Correct answer: D

Explanation

The correct answer is D because leveraging the existing team's experience to assess the planned work for the new resource helps optimize the current resources and workload. Options A and B reduce the project's scope or delay progress, which may not be ideal given the team's capabilities. Option C could introduce risks with a less experienced member that may not deliver the required quality.