Project Management Professional (PMP) — Question 810

During project execution, a project manager wants to involve the business lead before the users are involved in the project. However, the business lead is also engaged in another big project and cannot join this project meeting.

What should the project manager do first?

Answer options

Correct answer: B

Explanation

The correct answer is B because summarizing the changes and potential impacts allows the business lead to stay informed and provide input asynchronously. Option A might not ensure the business lead's perspective is adequately represented, C is impractical as it delays the project, and D does not address the need for the business lead's input specifically.