Project Management Professional (PMP) — Question 81

A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.
Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three.)

Answer options

Correct answer: A, B, E

Explanation

The correct actions are A, B, and E because they focus on prioritizing stakeholders, aligning their interests with project objectives, and assessing their influence, which are crucial for effective engagement. Option C, while useful, does not directly address the alignment with project needs or objectives. Option D is not advisable as it may overwhelm stakeholders with uniform communication rather than tailored engagement based on their influence and interest.