Project Management Professional (PMP) — Question 795

A product owner is trying to understand how many of the user stones have been completed within a 2-week sprint. How should the project manager approach this situation?

Answer options

Correct answer: D

Explanation

The correct answer is D because the burndown chart visually represents the progress of user stories completed during the sprint, making it easy for the product owner to understand the status. Options A and B do not directly provide data on completed user stories, and option C, while beneficial for communication, lacks the concrete data necessary for evaluation.