A product owner is trying to understand how many of the user stones have been completed within a 2-week sprint. How should the project manager approach this situation?
Answer options
- A. Use retrospectives to deliver the finished products.
- B. Invite the product owner to regular standup meetings.
- C. Have a face-to-face conversation with the product owner.
- D. Share the burndown chart with the product owner.
Correct answer: D
Explanation
The correct answer is D because the burndown chart visually represents the progress of user stories completed during the sprint, making it easy for the product owner to understand the status. Options A and B do not directly provide data on completed user stories, and option C, while beneficial for communication, lacks the concrete data necessary for evaluation.