Project Management Professional (PMP) — Question 790

A project manager has taken over an agile project. There have been several issues during product development due to unclear product requirements.

How should the project manager resolve this issue?

Answer options

Correct answer: B

Explanation

The correct answer is B because involving both the project team and the product owner facilitates clarity and consensus on product requirements, leading to a more effective solution. Option A focuses on task estimation, which does not directly address the underlying issue of unclear requirements. Option C is about reviewing issues rather than actively resolving the uncertainty, and Option D shifts focus to the definition of done, which is not a priority if the requirements are unclear.