Project Management Professional (PMP) — Question 760

A customer approaches the product owner with a new requirement and asks for a rough estimation to implement it. The outline of the task would be similar to a prior deliverable.

What should the product owner do to properly inform the customer?

Answer options

Correct answer: C

Explanation

The correct answer is C because revisiting the user story of the similar requirement allows the product owner to leverage past data on story points and velocity, leading to a more informed estimate. Option A does not directly address the estimation process, while B focuses on cost rather than time, and D, although useful for future references, does not provide immediate estimation insights.