Project Management Professional (PMP) — Question 732

A project manager is using a hybrid approach for a project. The project team created and reviewed the risk log with the stakeholders at the beginning of the project. However, midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies.

When should the risks be reviewed to ensure alignment between the project team and the stakeholders?

Answer options

Correct answer: D

Explanation

The correct answer is D, as reviewing risks during each iteration and review allows for timely updates and adjustments based on new information or changes in the project. Options A and B do not provide consistent opportunities for alignment, while C is too infrequent to ensure ongoing agreement.