Project Management Professional (PMP) — Question 728
A project manager is managing a new type of project for a traditional organization. The culture of the organization is not typically in support of change.
Which two factors should the project manager consider in developing the portion of the project plan related to culture? (Choose two.)
Answer options
- A. The relevant experience and qualifications of each team member.
- B. The amount of flexibility the team exercises while doing work.
- C. The amount of risk the organization is willing to accept.
- D. The speed the team can perform without compromising quality.
- E. The influence of the stakeholders on the project.
Correct answer: C, E
Explanation
The correct answers are C and E because understanding the organization's risk tolerance is crucial for navigating cultural resistance, and recognizing stakeholder influence is vital for gaining support. Options A, B, and D focus on team dynamics and performance metrics, which are less relevant to addressing cultural challenges within the organization.