Project Management Professional (PMP) — Question 712
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
Answer options
- A. Ensured project requirements were validated and communicated with the procurement team
- B. Ensured changing stakeholder needs and requests were properly monitored
- C. Ensured procurement contracts were able be canceled when situations like this arise
- D. Ensured that communications were sent to all stakeholders when requirements change
Correct answer: D
Explanation
The correct answer is D because effective communication with all stakeholders regarding changes in requirements is crucial to ensure alignment and understanding. Options A, B, and C, while important, do not directly address the need for clear communication about requirement changes, which is critical in this scenario.