Project Management Professional (PMP) — Question 706

An organization is using a hybrid delivery approach for a complex project. In the iteration review, a senior manager is asking for a complete redesign of the functionality presented. This may require a significant change in the technical architecture and an additional release.

What should the project lead do first?

Answer options

Correct answer: B

Explanation

The project lead should first discuss the redesign with the product owner because they are responsible for the project's vision and priorities. Understanding the product owner's perspective ensures that any significant changes align with stakeholder expectations and project goals. Discussing with the solution architect, technical lead, or development team may be important later, but the product owner needs to be consulted first to gauge the impact on the overall project direction.