Project Management Professional (PMP) — Question 675

A consultancy firm is finally selected and contracted for a project following an extensive and competitive procurement process. A few months into project execution, the client asks the project manager why the consultant is contracted for only 18 months instead of the full 32-month-long project. The project manager will need to carry out an unplanned second bidding process to ensure services are in place until the end of the project.

What should the project manager have done to prevent this?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of having a well-structured procurement management plan that includes all phases and client approval, which would ensure alignment on contract duration. Options B and C, while helpful, do not address the core issue of contract duration and planning, and D suggests a reactive approach rather than a proactive solution.