Project Management Professional (PMP) — Question 673

A project manager is preparing to start a new project in which the team members are distributed geographically across different countries. The project manager is using the communications management plan to engage the team members and find a communication method that suits everyone.

How should the project manager continually evaluate the effectiveness of the virtual team’s engagement?

Answer options

Correct answer: B

Explanation

The correct answer is B because collecting feedback directly from team members allows the project manager to understand their needs and preferences, leading to improved communication strategies. Options A and C focus on scheduling and building trust, which are important but do not directly evaluate engagement effectiveness. Option D emphasizes face-to-face meetings, which may not be feasible for geographically distributed teams.