Project Management Professional (PMP) — Question 671

While creating the work breakdown structure (WBS) with the team, the project manager highlights that the customer requested a proof of concept and will only continue the project based on the results of the proof of concept. A key team member insists that since this customer has a history of requesting proof of concepts and continuing with the projects, the team needs to plan for the whole project, not just the proof of concept.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because evaluating the scope of work as defined in the project charter will ensure that the project manager aligns the team's efforts with the client's requirements for a proof of concept before proceeding. The other options either ignore the client's current needs or focus on incomplete planning, which may lead to project misalignment.