A project manager is leading a project that is in the execution phase. During a team meeting, the project manager realizes that there are two team members who lack the technical skills required for some of the upcoming tasks.

What should the servant leader project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C, as providing training within the project budget directly addresses the skill gap and helps the team members become more effective. Option A puts the onus on the team members without offering practical support, while option B may not be necessary if training can resolve the issue. Option D unnecessarily escalates the problem to the sponsor instead of seeking a solution.