Project Management Professional (PMP) — Question 634

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint, the project manager notices that the team is not working as a cohesive unit.

Which two rules are appropriate for the project manager to instill in the team? (Choose two.)

Answer options

Correct answer: A, B

Explanation

The correct answers are A and B because working together daily fosters collaboration and alignment, which is crucial in agile environments. Striving for continuous improvement ensures that the team learns and evolves with each sprint. Options C, D, and E do not promote team cohesion or ongoing development in the same way.