Project Management Professional (PMP) — Question 627
A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.
What should the project lead do?
Answer options
- A. Invite the board member to a separate demo.
- B. Invite the board member to the next sprint review.
- C. Invite the board member to the next sprint retrospective.
- D. Invite the board member to the next daily standup.
Correct answer: B
Explanation
The correct answer is B, as the sprint review is specifically designed for stakeholders to evaluate work completed and provide feedback. Options A, C, and D do not offer the same opportunity for the board member to observe the project's deliverables being reviewed and discussed with the team.