A project manager is leading a technically complex project. The project is part of a strategic program of work and the first to use an agile approach. One of the board members is interested in attending a meeting to see how the delivery of the project scope is progressing.

What should the project lead do?

Answer options

Correct answer: B

Explanation

The correct answer is B, as the sprint review is specifically designed for stakeholders to evaluate work completed and provide feedback. Options A, C, and D do not offer the same opportunity for the board member to observe the project's deliverables being reviewed and discussed with the team.