Project Management Professional (PMP) — Question 624

A project manager is assigned to a strategic communication project that involves subject matter experts (SMEs), interns, and new recruits. The project manager discovers that the project is not gaining much traction due to knowledge gaps from the interns. The budget for training is exhausted and the project needs to be delivered without delay.

Which two actions should the project manager take? (Choose two.)

Answer options

Correct answer: A, D

Explanation

The correct answers, A and D, focus on addressing the knowledge gaps directly by identifying the issues and providing mentorship. Option B is not feasible due to the exhausted budget, while option C ignores the problem and risks project failure. Option E does not solve the immediate knowledge gap issue and could demoralize the team.