Project Management Professional (PMP) — Question 596

During the early phases of a project, mitigation actions were not executed in a timely manner; therefore, the project schedule was impacted. Several project stakeholders are now frustrated with the delays.

What should the project manager have done to manage the issue?

Answer options

Correct answer: C

Explanation

The correct answer is C because the project manager should have identified the right response to the issue and ensured it was executed to prevent further delays. Options A and B focus on reporting and monitoring, which are reactive rather than proactive measures. Option D is important but comes after the appropriate response has been decided and implemented.