Project Management Professional (PMP) — Question 592
In a project progress review meeting, the end user raises concern about the quality of the construction of the project. What should the project manager do next?
Answer options
- A. Request a special technical meeting.
- B. Refer to the requirements document.
- C. Review the risk management plan.
- D. Review all implementation checklists.
Correct answer: B
Explanation
The correct answer is B because referring to the requirements document allows the project manager to verify if the construction meets the specified standards and requirements. Options A, C, and D, while potentially useful, do not directly address the immediate concern about construction quality and may delay finding a resolution.