Project Management Professional (PMP) — Question 584
During the implementation stage of a project, a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.
What should the project manager do?
Answer options
- A. Ask the human resources director to appoint a senior team leader
- B. Inform the project sponsor about the possible delay
- C. Directly manage the project team to avoid project delays
- D. Provide mentoring to the newly appointed team leader
Correct answer: D
Explanation
The correct answer is D because providing mentoring to the team leader can help develop their management skills and improve the team's performance moving forward. Option A does not address the immediate need for improvement and may disrupt team dynamics. Option B, while informative, does not resolve the immediate issue of task management. Option C removes responsibility from the team leader, hindering their growth and development.