Project Management Professional (PMP) — Question 578

A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer. The SMEs captured various process deviations without sharing with the project team.
How can the project manager ensure knowledge transfer across the team?

Answer options

Correct answer: D

Explanation

The correct answer is D because sharing knowledge transfer documents in the PMIS ensures that all team members have access to the necessary information regarding process deviations. Options A and B focus on retrospective actions rather than immediate knowledge sharing, while option C, although beneficial, does not directly address the immediate need for sharing the captured information.