Project Management Professional (PMP) — Question 576

A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer, D, emphasizes understanding the underlying reasons for stakeholder disagreement, allowing for targeted resolutions. Options A, B, and C do not address the root causes of the conflict and instead focus on administrative tasks or meetings that may not resolve the fundamental issues at hand.